Delhi Pike Thoroughfare Project
Project Status Details
| Item | Start Date | End Date | Status | % Complete |
| Execute and record agreements | 11/24/2006 | 12/15/2009 | Completed | 100 |
| Prepare draft scope | 1/27/2009 | 1/27/2009 | Completed | 100 |
| Review and finalize draft scope | 1/28/2009 | 2/4/2009 | Completed | 100 |
| Post scope on website | 2/6/2009 | 2/6/2009 | Completed | 100 |
| Obtain consultant qualifications | 2/20/2009 | 3/6/2009 | Completed | 100 |
| Finalize consultant ratings | 3/6/2009 | 3/20/2009 | Completed | 100 |
| Request proposal from consultant | 3/9/2009 | 3/9/2009 | Completed | 100 |
| Obtain proposal | 3/23/2009 | 4/3/2009 | Completed | 100 |
| Prepare agreement | 3/25/2009 | 4/1/2009 | Completed | 100 |
| Legal review of agreement | 3/26/2009 | 4/9/2009 | Completed | 100 |
| Consultant signature on agreement | 4/10/2009 | 4/22/2009 | Completed | 100 |
| Send agreement to BOCC | 4/23/2009 | 4/23/2009 | Completed | 100 |
| Obtain agreements for ROW | 4/24/2009 | 10/28/2009 | Completed | 100 |
| Obtain inter-governmental agreement | 10/28/2009 | 10/28/2009 | Completed | 100 |
| Agreements approved by BOCC | 11/23/2009 | 11/23/2009 | Completed | 100 |
| Send executed agreement to consultant | 12/16/2009 | 12/16/2009 | Completed | 100 |
| Submission of Phase A drawings | 12/17/2009 | 1/25/2010 | Completed | 100 |
| Anticipated design time | 12/17/2009 | 4/30/2010 | Completed | 100 |
| Request title searches | 12/18/2009 | 1/1/2010 | Completed | 100 |
| Obtain title searches | 1/8/2010 | 1/8/2010 | Completed | 100 |
| Obtain proposal for appraisals | 1/8/2010 | 1/22/2010 | Completed | 100 |
| Prepare appraisal agreement | 1/25/2010 | 2/1/2010 | Completed | 100 |
| Legal review of appraisal agreement | 2/8/2010 | 2/22/2010 | Completed | 100 |
| Phase A review meeting | 2/17/2010 | 2/17/2010 | Completed | 100 |
| Submission of drainage plans | 2/17/2010 | 2/17/2010 | Completed | 100 |
| Submission of traffic maintenance plan | 2/17/2010 | 2/17/2010 | Completed | 100 |
| Send agreement to appraiser | 2/22/2010 | 3/15/2010 | Completed | 100 |
| Send plans to utility companies | 2/23/2010 | 2/23/2010 | Completed | 100 |
| Submission of Phase B drawings | 2/24/2010 | 3/18/2010 | Completed | 100 |
| Write inter-governmental agreement | 3/1/2010 | 3/26/2010 | Completed | 100 |
| Drainage review meeting | 3/3/2010 | 3/3/2010 | Completed | 100 |
| Maintenance of traffic review meeting | 3/3/2010 | 3/3/2010 | Completed | 100 |
| Send appraisal agreement to BOCC | 3/16/2010 | 3/16/2010 | Completed | 100 |
| Submission of traffic control plans | 3/18/2010 | 3/18/2010 | Completed | 100 |
| Begin negotiations | 3/19/2010 | 4/8/2010 | Completed | 100 |
| Phase B review meeting | 3/26/2010 | 3/26/2010 | Completed | 100 |
| Traffic control review meeting | 3/26/2010 | 3/26/2010 | Completed | 100 |
| Obtian permits | 3/26/2010 | 3/26/2010 | Completed | 100 |
| Submission of project specifications | 3/26/2010 | 3/26/2010 | Completed | 100 |
| Obtain approvals for agreement | 3/29/2010 | 4/28/2010 | Completed | 100 |
| Consultant submits FINAL plans, specifications, notes and quantities | 3/31/2010 | 3/31/2010 | Completed | 100 |
| Utility relocation completed | 3/31/2010 | 3/31/2010 | Completed | 100 |
| Obtain appraisals | 4/16/2010 | 4/16/2010 | Completed | 100 |
| Specification/quantity review meeting | 4/16/2010 | 4/16/2010 | Completed | 100 |
| Appraisal negotiations completed | 4/16/2010 | 4/16/2010 | Completed | 100 |
| Send agreement and contract to BOCC | 4/29/2010 | 4/29/2010 | Completed | 100 |
| Send bid package to BOCC | 5/26/2010 | 5/26/2010 | Completed | 100 |
| BOCC advertises for bids | 5/29/2010 | 5/29/2010 | Completed | 100 |
| Bid opening | 6/17/2010 | 6/17/2010 | Completed | 100 |
| Bid tabulation and review | 6/17/2010 | 6/17/2010 | Completed | 100 |
| Execute and record agreement | 6/20/2010 | 7/23/2010 | Completed | 100 |
| Contract signing | 7/20/2010 | 7/20/2010 | Completed | 100 |
| Preconstruction meeting | 7/29/2010 | 7/29/2010 | Completed | 100 |
| Access management construction | 8/19/2010 | 1/7/2010 | Completed | 100 |
| Traffic signal system installation | 8/19/2010 | 2/25/2010 | Completed | 100 |
| Park Drive construction | 8/19/2010 | 12/3/2010 | Completed | 100 |
| Pavement markings | 10/11/2010 | 11/19/2010 | Completed | 100 |
| New pavement installation | 10/27/2010 | 11/13/2010 | Completed | 100 |